Feb 2019

 
Construction update of some of our sites
 
Gulmohar Park, New Delhi
Construction start date: Sep 2018
Picture Taken: Feb 2019
Time under development: 5 Months
Activities
1. Brickwork has been started on all floors.
2. Casting of Stilt, Ground, First and Second floor is complete.
3.
Casting of Third Floor in progress. 
Gulmohar Park, New Delhi
Slab casting of 3rd floor in progress. 
Kohat Enclave, Pitampura, New Delhi
Construction start date: June 2018
Picture Taken: Feb 2019
Time under development: 8 Months
Activities
1. Flooring work in progress on all floors. 

2. False Ceiling work in progress. 
3. Tiling work in progress. 
4. Casting of Stilt, Ground, First Floor and Second Floor slab complete.
Kohat Enclave, Pitampura, New Delhi
Tiling work in progress.
CP-Block, Pitampura, New Delhi
Construction start date: Nov 2018
Picture Taken:  Feb 2019
Time under development:  3 Months
Activities
1. Casting of Stilt and Ground Floor slab is complete.

2. Casting of First Floor slab in progress. 
CP-Block, Pitampura, New Delhi
Blockwork in Stilt Floor in progress. 
C-Block, South City-1, Gurugram
Construction start date: June 2018
Picture Taken: Feb 2019
Time under development: 8 Months
Activities
1. Casting of Stilt, Ground, First, Second floor Complete. 

2. Flooring work in progress on all floors. 
C-Block, South City-1, Gurugram
External plastering in progress. 
Palam Vihar, Gurugram
Construction start date: June 2018
Picture Taken: Feb 2019
Time under development: 8 Months
Activities
1. Casting of Ground, First and Second Floor complete. 
2. Flaster work in progress on all floors. 
Palam Vihar, Gurugram
Internal plastering in progress. 
Project A, DLF Phase 1, Gurugram
Construction start date: Dec 2018
Picture Taken: Feb 2019
Time under development: 2.5 Months
Activities
1. Foundation work complete. 
2. Clasting of basement slab in progress. 
Project A, DLF Phase 1, Gurugram
Casting of basement slab in progress. 
Blackcat Enclave, Greater Noida
Construction start date: Sep 2018
Picture Taken: Feb 2019
Time under development: 5 Months
Activities
1. POP plastering completed in ground floor bedrooms.
2. Front elevation railing work has been completed.
3. Front elevation plaster completed.
4. Wall plaster in all bathrooms completed.
Blackcat Enclave - Greater Noida
Front elevation railing work has been completed.
Emaar Marbella, Gurugram
Construction start date: Jan 2019
Picture Taken: Feb 2019
Time under development: 1.5 Month
Activities
1. Foundation work in progress. 
Emaar Marbella - Gurugram
Foundation work in progress. 
East Patel Nagar, New Delhi
Construction start date: Nov 2018
Picture Taken: Feb 2019
Time under development: 2.5 Months
Activities
1. Foundation work complete.
2. Casting of stilt slab in progress. 
East Patel Nagar - New Delhi
Brickwork on stilt level complete. 
Sector 51, Gurugram
Construction start date: Nov 2018
Picture Taken: Feb 2019
Time under development: 2.5 Months
Activities
1. Foundation work complete.
2. Casting of 1st slab complete. 
3. Casting of 2nd slab complete. 
Sector 51 - Gurugram
Casting of 2nd slab complete. 
Build your Home in Delhi NCR at just Rs 1850*/sq.ft.
 
View Details
Or 

Call 9599818105
Never miss another update from us!
Prithu Homes 
Vinimay Developers Pvt Ltd. 15D Atma Ram House. No. 1 Tolstoy Marg, New Delhi - 110001. 
sales@prithu.in 
+91 9599818105 
www.prithu.in
Copyright © 2019 Prithu Homes, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.