Jan 2019

 
Construction update of some of our sites
 
Gulmohar Park, New Delhi
Construction start date: Sep 2018
Picture Taken: Jan 2019
Time under development: 4 Months
Activities
1. Casting of slab for Basement, Stilt, and Ground Floor complete. 
2. Slab for 1st floor has been laid.
3. Brickwork has been started on 
the basement and stilt floor. 
Gulmohar Park, New Delhi
Slab casting for 1st floor in progress. 
Kohat Enclave, Pitampura, New Delhi
Construction start date: June 2018
Picture Taken: Jan 2019
Time under development: 7 Months
Activities
1. Plasterwork in progress on mumty.
2. Flooring work has started. 
Kohat Enclave, New Delhi
Plasterwork in progress on mumty
CP-Block, Pitampura, New Delhi
Construction start date: Nov 2018
Picture Taken:  Jan 2019
Time under development:  2 Months
Activities
1. Casting of 1st slab is complete. 
2.
Casting of 2nd slab in progress. 
CP-Block, Pitampura, New Delhi
Casting of 2nd slab in progress. 
C-Block, South City-1, Gurugram
Construction start date: June 2018
Picture Taken: Jan 2019
Time under development: 7 Months
Activities
1. Flooring work has started on all floors. 
2. Services work in progress on all floors which includes provisioning for ACs, electrical work, and plumbing work. 
3. Plasterwork in progress on all floors. 
C-Block, South City-1, Gurugram
Casting of slabs complete for all the floors. Flooring work in progress. 
Palam Vihar, Gurugram
Construction start date: June 2018
Picture Taken: Jan 2019
Time under development: 7 Months
Activities
1. C
asting of slabs complete for all 2 floors. 
2. Brickwork has been started on all the floors. 
3. Services work in progress on all floors which include provisioning for ACs, electrical work, and plumbing work. 
Palam Vihar, Gurugram
Casting of slabs complete for all the floors. 
 
 
Project A, DLF Phase 1, Gurugram
Construction start date: Dec 2018
Picture Taken: Jan 2019
Time under development: 1.5 Month
Activities
1. Foundation work complete. 
2. Clasting of basement slab complete. 
Project A, DLF Phase 1, Gurugram
Casting of basement slab complete. 
 
Blackcat Enclave, Greater Noida
Construction start date: Sep 2018
Picture Taken: Jan 2019
Time under development: 4 Months
Activities
1. Brickwork has been completed on all floors. 
2. Services work in progress on all floors which include provisioning for ACs, electrical work, and plumbing work. 
3. Plasterwork in progress. 
Blackcat Enclave - Greater Noida
Plasterwork in progress. 
 
Emaar Marbella, Gurugram
Construction start date: Jan 2019
Picture Taken: Jan 2019
Time under development: 0.5 Month
Activities
1. Foundation work in progress. 
Emaar Marbella - Gurugram
Foundation work in progress. 
 
East Patel Nagar, New Delhi
Construction start date: Nov 2018
Picture Taken: Jan 2019
Time under development: 1.5 Months
Activities
1. Foundation work in progress. 
East Patel Nagar - New Delhi
Foundation work in progress. 
 
Sector 51, Gurugram
Construction start date: Nov 2018
Picture Taken: Jan 2019
Time under development: 1.5 Months
Activities
1. Foundation work complete.
2.
Casting of 1st slab in progress. 
Sector 51 - Gurugram
Foundation work in progress.
 
Build your Home in Delhi NCR at just Rs 1850*/sq.ft.
 
View Details
Or 

Call 9599818105
 
Never miss another update from us!
 
Prithu Homes 
Vinimay Developers Pvt Ltd. 15D Atma Ram House. No. 1 Tolstoy Marg, New Delhi - 110001. 
sales@prithu.in 
+91 9599818105 
www.prithu.in
Copyright © 2019 Prithu Homes, All rights reserved.


Want to change how you receive these emails?
You can update your preferences or unsubscribe from this list.