Construction Updates

X

2019 Construction Update

January 2019

Construction update of some of our sites

project_img 0
Gulmohar Park, New Delhi

Construction start date:

1 January, 2019

Picture Taken:

31 January, 2019
Time under development: 1 Months
Activities
  • 1. Foundationwork complete.
  • 2. Casting of basement and stilt slab complete.

February 2019

Construction update of some of our sites

project_img 0
Gulmohar Park, New Delhi

Construction start date:

1 February, 2019

Picture Taken:

31 March, 2019
Time under development: 2 Months
Activities
  • Foundationwork complete.
  • Casting of all four slabs complete.
  • Services work has been started on all floors which include provisioning for ACs, electrical work, and plumbing work.