Plaster work complete on all the floors. Floor polishing in progress.
August , 2018
False ceiling work complete on all floors.
July , 2018
Wall tiles being installed in the bathrooms.
April , 2018
Provisioning for Air Conditioners being done on all the four floors. All the wall chasing is done through specialized machines to get clean grooves.
March , 2018
Space has been left beforehand for easy installation of skirting tiles. This method results in a better flooring finish.
February , 2018
Construction of Mumty in progress.
January , 2018
Pipes have been provided at the top of each underground tank so that overflowing water can be collected separately in a different tank, preventing spillage on the floor.
December , 2017
Overview of the stilt area. On the left, underground water tank is being made.
November , 2017
Plastic cover is applied to the neighbouring wall to protect it from various construction procedures.