X

Project B, S-Block, GK - 1

  • 208 sq. Yards
  • Stilt + 4 Floors
  • 3BHK
  • Construction Start: April , 2016
  • Completion: June , 2017

Project Description

This project is located in the S-Block of Greater Kailash 2. It is built on a 300 sq. yards plot and has Stilt + 4 floors. Each floor follows a 3BHK configuration. This is Prithu’s first project as a construction company in Greater Kailash 2.

There are many construction companies in Greater Kailash 2 but very few provide parking facilities in the stilt area. The stilt of this home can easily accommodate 8 cars. Each floor has 2 reserved parking spots which are independent of the other floors i.e. no interference from the neighbours if they want to park or take their car out.

The project is just a 5-minute walk away from the popular M-Block market in Greater Kailash – 2.

section_icon

Construction Pictures

Putty & base coat of paint under progress

September , 2018

False ceiling and plaster work done on all floors. Floor polishing in progress.

Putty & base coat of paint under progress, wiring completed, flooring completed

September , 2018

Lift installation work in progress.

Bathroom wall tile work under progress

July , 2018

False ceiling work in progress on all floors.

False celling framing work under progress

July , 2018

Tiles are being installed in bathrooms on all floors.

UPVC plumbing work under progress

April , 2018

Plumbing work in progress on all the floors.

Block work under progress

April , 2018

Brickwork complete on all the 4 floors.

Gypsum plaster one coat work under progress

March , 2018

Gypsum plaster samples have been laid out on the wall for quality and visual test.

Flyash Block work under progress

March , 2018

Partition walls being laid out at the GK 2 site.

Block work under progress

March , 2018

The front balcony parapet being erected.

Electrical wall conduit work under progress

March , 2018

An overview of the ground floor.

March , 2018

Conduits being laid on the ground floor.

barricading for construction work

March , 2018

Plumbing holes have been drilled using core cutting machine.

Flyash Block work under progress

March , 2018

An external view of the GK – 2 site.

Rain water tank casting work

February , 2018

Underground tanks being constructed at Gk -2 Site.

February , 2018

The stilt area being prepared to cast a thin layer of RMC to even out the floor.

February , 2018

An overview of the terrace at the GK – 2 site. Mumty is being constructed on the left.

Rain water tank casting work

February , 2018

Construction of rainwater harvesting tank in progress.

Rain water tank casting work

February , 2018

Construction of rainwater harvesting tank in progress.

Block work under progress

February , 2018

Blockwork in progress on the first floor.

Rain water tank casting work

January , 2018

Construction of underground water tanks almost reaching the completion stage.

January , 2018

An overview of the first floor. On the left, partition walls are being constructed with ACC blocks. Proper plastic covers have been placed so the neighboring walls don’t get affected.

January , 2018

January ’18</h4> <p><span> Construction of partition walls with AAC blocks being done at GK – 2 site. AAC blocks have numerous advantages over bricks as they provide insulation against heat and sound, provide better protection against seepage, have better strength, etc.

Slab steel work under progress

January , 2018

anuary ’18</h4> <p><span> Shafts being outlined with ACC blocks. Proper shuttering and netting has been appropriately provided for a neat and secure construction process.

Steel reinforcement work under progress

January , 2018

January ’18</h4> <p> <span>Proper protection has been provided wherever necessary so that least possible intrusion or discomfort is caused to the neighboring structures.

December , 2017

Underground water tank under progress

December , 2017

Construction of underground water tank being done in the stilt area.

December , 2018

Netting has been provided appropriately for safety and a hassle-free construction process.

Basement excavation work under progress

November , 2017

Wooden shuttering has been done to properly encase the concrete while the casting is done and also to create a sturdy temporary structure.

Beam shuttering work under progress

November , 2017

Wooden shuttering has been done to properly encase the concrete while the casting is done and also to create a sturdy temporary structure.

Beam shuttering work under progress

November , 2017

November ’17&lt;/h4&gt; &lt;p&gt;&lt;span&gt;Proper height corrugated sheet enclosure is made on our construction sites to create a systemized and cohesive working environment and also to minimize the intrusion of construction on the neighbourhood.

barricading for construction work

November , 2017

Steel scaffolding ensures better safety and stability than any other materials such as a timbre, aluminium etc.

curing work under progress

November , 2017

We use high quality curing compound to preserve the moisture in concrete so that it obtains its required strength planned during structure design. This process is traditionally done through ‘tarai’ where water is sprinkled on concrete for 7-15 days but that process causes quality inconsistencies because it’s a manual process with no quality specifications defined.

Floor Plans & Renders

Kickstart your Home Construction with Prithu Homes

Enter your details. We will contact you.

section_icon

Explore Our Home Projects

Explore Our Home Projects